Project Team meetings
As of 22 June 2011, the new Learning Environment Operations group (LEO) replaced UW-ACE Operations (Aesops). Minutes are now in Sharepoint.
Sep. 3, 2010 - 18 Mar. 2011 meeting minutes are on SharePoint as RFP responses are discussed.
- 18 March 2011 (agenda)
- 2 March 2011 (agenda)
- 16 February 2011 (agenda) (minutes on SP)
- 01 February 2011 (agenda) (minutes on SP)
- 17 January 2011 (agenda)
- 15 December 2010 (agenda) (minutes on SP)
- 6 December 2010 (agenda) (minutes on SP)
- 9 November 2010 (agenda) (minutes on SP)
- 20 October 2010 (agenda) (minutes on SP)
- 5 October 2010: Project Retreat - RFP analysis, next steps
- 22 September 2010 (agenda) (minutes on SP)
- 3 September 2010 (agenda) (minutes on SP)
- 26 August 2010
- 28 July 2010 (agenda only)
- 21 July 2010
- 7 July 2010 (agenda only)
- 23 June 2010
- 2 June 2010
- 18 May 2010
- 5 May 2010
- 20 April 2010
- 9 April 2010
- 24 Mar 2010 (meeting cancelled, e-update)
- 9 March 2010 (agenda only)
- 24 Feb 2010 (meeting cancelled, e-update)
- 10 Feb 2010 (RFP process/progress, Bb/ANGEL focus groups)
- 27 Jan 2010 (STAC, RFP, sandboxes, assistant, Mac)
- 13 Jan 2010 (communic., time lines, proj assistant)
- 9 Dec 2009 (agenda only)
- 24 Nov 2009 (Laurier LMS presentations)
- 10 Nov 2009 (Educause update, Nov. 4 D2L update)
- 29 Oct 2009 (agenda only) (LMS Needs subgroup)
- 23 Sep 2009 (Selection approach, needs, RFI vs RFP)
- 2 Sep 2009 (P. Carr, student input, use cases, LMS list)
- 28 Jul 2009 (Use cases, charter)
- Kick-off meeting, 22 June 2009
Subgroup Meetings: LMS Needs Analysis
Project Communications
PROJECT COMMUNICATIONS SITE
- UCIST, 17 Feb. 2012
- UCIST, 20 Jan. 2012
- ITAC Analytics, 13 Jan. 2012
- ITAC, 13 Jan. 2012
- CTSC, 12 Jan. 2012
- UCIST, 6 Jan. 2012
- Bulletin update, (Word file)
- UCIST, 25 Nov. 2011
- Friday a.m. seminar "show and tell", 25 Nov. 2011
- STAC, Nov. 2011
- D2L Ontario Users Group, 14 Oct. 2011
- UCIST, 16 Sep. 2011
- Friday a.m. seminar, 9 Sep. 2011
- CTSC (email summary), 8 Sep. 2011
- Bulletin update, 8 Sep. 2011
- Email to all instructors about roll-out and status, 7 Sep. 2011
- CANHEIT 2011 presentation panel, 7 June 2011 (images cut to reduce size)
- Friday a.m. seminar, 6 May 2011
- Bulletin - spring courses, 2 May 2011
- UCIST, 29 Apr. 2011
- OPEN HOUSE, 19 Apr. 2011
- ITAC, 18 Apr. 2011
- UCIST, 1 Apr. 2011
- STAC, 24 Mar. 2011
- CTSC, 24 Mar. 2011
- Bulletin announcement - selection of D2L!, 17 Mar. 2011
- UCIST update, 4 Mar. 2011 (response to feedback on recommendations; accepted!)
- UCIST update, 18 Feb. 2011 (Project recommendations)
- STAC, 15 Feb. 2011
- UCIST update, 28 Jan. 2011 (RFP info)
- UCIST update, 14 Jan. 2011 (RFP info)
- UCIST update, 16 Dec. 2010 (email summary of completion of RFP analysis, next steps)
- UCIST update, 10 Dec. 2010 (email summary in email to UCIST and project team)
- UW-ACE User's Group, 9 Dec. 2010
- WatITis, 7 Dec. 2010
- UCIST update, 12 Nov. 2010 (RFP info ) - cut short at UCIST
- Bulletin communications site announcement - 9 Nov. 2010
- Email to all instructors about new communications site - 5 Nov. 2010
- ITAC (same as CTSC), 27 Oct. 2010
- Friday a.m. seminar, 22 Oct. 2010
- CTSC, 21 Oct. 2010
- UCIST update, 15 Oct. 2010 - no slides, RFP info
- STAC, 14 Oct. 2010
- UCIST update, 1 Oct. 2010 - not public, RFP info
- UCIST update, 17 Sep. 2010 - not public, RFP info
- UCIST, 25 June 2010 (postponed from May)
- STAC, 3 June 2010
- UCIST 14 May (postponed from 16 Apr.)
- STAC part 2, 10 Feb. 2010
- CTSC (same as ITAC), 28 Jan. 2010
- ITAC, 27 Jan. 2010
- STAC, 20 Jan. 2010
- Friday a.m. seminar, 15 Jan. 2010
- UCIST, 8 Jan. 2010
- Bulletin project update - 4 Jan. 2010
- WatITis, 8 Dec. 2009
- Friday a.m. seminar, 25 Sep. 2009
- UCIST - Sale of ANGEL, 29 May 2009
- Bulletin "Business as usual" (ANGEL sale) 8 May 2009
|
Project Documentation
- Project Charter
- Project Team Members
- Mailing lists (on lists.uwaterloo.ca): lms_select_core; lms_select_resource
- Subgroups
- LMS Needs Analysis (Aldo, Andrea, DaveB, Jane, Lorne, Skid)
- Team Leads (starting January 2011)
- Implementation/Integration (Lorne)
- Orchestration (Jan)
- Migration (Jane)
- Reuse Topics (Dave)
- Functionality (Andrea - for Sean)
- ePortfolio (Katherine)
- Analytics (Jane)
- Content/Standards - group
Resources for team members only
Supplementary Resources (open)
- OLE Project (previous look at online learning environment and needs; preceded Angel sale)
- Andrea's notes from EDUCAUSE webcasts:
- Needs Analysis Template (Word doc)
|